University of Toronto Schools Renovation:

  • Week of March 11  Entrance restoration continues.  South stairwell to be demolished.
    On March 14, demolition of 713 Spadina Avenue commences. This will take approximately 2 weeks to complete.  During the demolition, one can expect higher than usual noise levels and potentially higher dust levels.  We recommend keeping windows closed during this time.
  • Week of March 25   Demolition of garages located behind 4 and 6 Washington Avenue. Community members can expect to see activity on the work site along with standard construction-type noise

Robarts Commons:
For the most updated information, please refer to the following link: https://onesearch.library.utoronto.ca/robarts-common/home

Overall, work will take place from Monday to Friday between 7 a.m. and 7 p.m.; Saturday from 9 a.m. to 7 p.m., and which adheres to the City of Toronto noise bylaws.

Additional contact:  Sean O’Molloy, Senior Project Manager, Project Management, University of Toronto, Ph 416-978-8163 or sean.omolloy@utoronto.ca

 